Tuesday 1 December 2009

Day16: Opening Night

Wow - what a massive improvement.  We were greeted with canapés and wine before touring the new establishment.  Such a huge difference!  You really MUST go and see for yourself!  I got a picture of the new menu and noted that wifi is now available for free :)



Sunday 29 November 2009

Day14: No Entry

Hmm - that's it guys, went back tonight to try and get some 'final' pics but my usual entry was barred.  Guess they finally figured out how I was getting in....  So, my secretive two weeks of snooping is over.  Still, the new look pub opens on Tue so you can see for yourselves!  Who knows, I might even be standing next to you at the bar :)

Thanks for reading...
/rakh1

Friday 27 November 2009

Day12: Furniture and wallpaper

The pub looked deserted so I snuck in once more this evening.  Some significant changes have occured.  There is now a lot of furniture in place - most covered in dark brown leather.  The carpets (red) are ready to be installed and the wooden flooring covered up for protection as they finish off painting.  Most notable though is the wallapaper - bold flowery patterns!  Best of there are numerous pictures on the wall depiciting Knebworth - the church, the house, etc etc.  It looks fantastic.  There are pumps behind the bar but no sign of the new ales yet...


Wednesday 25 November 2009

Day10: Carpets Arrive

I managed to sneak in for a few moments tonight before noise from upstairs made me beat a hasty retreat.  My guess is that they *must* be on to this blog by now and are trying to catch me.  Even so I managed a couple of quick snaps to show the work done today.  You can see most of the flooring is down and the carpets have arrived.  The boxes of flyers from yesterday have vanished - wouldn't be surprised if they hit the high street tomorrow on a promotional charge!  I'm not going to be around, but if you see them grab a pic - let me know in the comments with a contact email and I'll get it from you for the blog.


Tuesday 24 November 2009

Day9: Flooring and Promotions

Another evening's success and I've gathered a fair amount of information this time.  You can see the oak flooring going down and I also found a box of wall paper which gives an idea of the final look.  They've also done a lot more painting and fitted a disabled toilet.  The prize bit of info tonight was the finding of some promotional leaflets detailing an upcoming 'cook off' competition and confirmation that the pub quiz will be staying - see the first image :)


Monday 23 November 2009

Day8 - Structually complete

Last night my usual entrance presented itself and I snuck inside for an update.  There has been a huge amount of work completed over the weekend.  I think that all the structural changes now look complete and they are starting to paint and decorate.  The ladies toilets are nearly complete and the main wall, that you see when you first enter the (now reversed) main doors, has been filled in.  Still no sign of what will be behind the bar but I snapped an updated set of plans taped to a wall.  I also saw a load of boxes piled in the middle of the back bar area.  I tore open a corner and took a photo of what looks like the new flooring - oak I think.


Day5/Day6/Day7: No News

Apologies to all - I got tied up over the weekend and did not manage to pay a visit. Rest assured that will soon be put right though - I hear there have been quite a few changes over the weekend! Check back tonight for Day8.